Hello Anuj,
Please refer 1745312 - MRP creates redundant proposals though there are fixed future receipts which can cover the requirements.
The fixed future receipt lies out of the rescheduling horizon or it is not selected for rescheduling.
It is only considered for rescheduling when it lies in the rescheduling horizon and it is selected to be considered for rescheduling in the customization.
In-house production.
- In-house production time. (Maintained in the material master, working days.)
- GR processing time. (Maintained in the material master, working days.)
MRP group in OMDW it has higher priority than the one of plant. If the MRP group is entered in the material master but there is no value in OMDW for MRP group then the horizon for plant maintained is read.
Best Regards,
R.Brahmankar