Re: Using Planned orders effectively in MRP

$
0
0

Thanks Rupesh for your reply.

Pls clarify following cases:

Suppose I have a requirement for 'X' material on 31st sept.

let us assume 2 cases

1) material having lead time 10 days

2) material with lead time 60 days.

in first cast I want the PR to be generated on 31st-10days=21st Sept

while in second case PR generation should be immediate.

If I use MRP control parameter 2 for Create Pur Req in first case it satisfies my need but in second case Planned order is given and I dont know when it would convert to PR

which parameters I should maintain in SAP to avoide PR list but with material surety?

Regards,

Mahesh